Operating principle
Water AERATION method: unpurified water flows through the aeration tank, where it is mixed with air, and oxidizes the iron and manganese into solid particles. The solid particles are accumulated in the filter tank and then washed in the sewers.
Filtration materials used in water purification are PIROLOX or BIRM and quartz sand layer consisting of various fraction grains (0.2 mm - 5mm).
Technical data:
Purification yields | 1,2 m3h or 20 l/min |
Maximum flow rate | 4,5 m3h |
Quantity of filtering layer | 45 l |
Operating required minimum water pressure | 2.0 Bar |
The required frequency of regeneration | once in 1...7 days |
Duration of regeneration (flushing) | 16...22 min |
Inlet / outlet diameter of control mechanism | DN 1" external thread |
Wastewater outlet diameter | DN 3/4" external thread |
Control unit electrical connection | 220 V |
Oil free air compressor capacity | 8,0 Bar max. |